using version 5.3.1
when using the taskNonWorkingTime on the Gantt the darkened area for non working times set in my calendar bleeds into the day before and after. this does not happen with the regular NonWorkingTime with the same calendar assigned as the project default
{
"id": 6,
"name": "7 Day WW",
"unspecifiedTimeIsWorking": false,
"intervals": [
{
"recurrentStartDate": "on Sunday, Monday, Tuesday, Wednesday, Thursday, Friday, Saturday at 9:00",
"recurrentEndDate": "on Sunday, Monday, Tuesday, Wednesday, Thursday, Friday, Saturday at 17:00",
"isWorking": true
}
]
}
i have project hoursPerDay set to 8