Odoo Gantt Chart
Posted: Tue Feb 15, 2022 9:22 am
by shatha
Dears,
Since we are using Odoo Gantt Chart for our projects it is very important to stick to the timeline,
The issue that we faced that Gantt Chart is working on Europe working days (Monday - Friday) but here in middle east (Oman) our working days from (Sunday- Thursday) so basically it is counting the weekends as its a working days.
could you please share with us any solution to solve the problem. or is there any chance to change it according to our working days.
Re: Odoo Gantt Chart
Posted: Tue Feb 15, 2022 11:11 am
by Terence
- Screenshot 2022-02-15 at 10.08.50.png (283.33 KiB) Viewed 1541 times
In the settings page you can set the week startday in the Gantt configuration object.
https://www.bryntum.com/docs/gantt/api/Scheduler/view/TimelineBase#config-weekStartDay
Re: Odoo Gantt Chart
Posted: Thu Feb 17, 2022 10:13 am
by shatha
we try to copy the code to our setting but as it shows below in the attached photo, the calendar configuration object \table does not appear in our settings, is this because of version that we are using or not?
Note: the code is not running as well
We are using Odoo 13
Bryntum Gantt for Odoo 4.3.1
Re: Odoo Gantt Chart
Posted: Thu Feb 17, 2022 1:41 pm
by Terence
Could you update to the latest sources?
Re: Odoo Gantt Chart
Posted: Wed May 25, 2022 11:51 am
by shatha
Dear Mr.Terence
According to above dissection, we successfully changed the start working days as it show in the picture arrow (1) , but we still can not change the date in the sub task as it show in the picture arrow (2) as we tried to shift the date to Sunday and it failed (it does not change the date according to our working days )
Re: Odoo Gantt Chart
Posted: Wed May 25, 2022 12:10 pm
by Terence
I am not able to reproduce on https://odoo-gantt.bryntum.com
- Screenshot 2022-05-25 at 12.06.07.png (7.05 KiB) Viewed 1243 times
I am able to move a task to Sunday. Can you elaborate what is the situation and what you expect to be changed?
Is the project auto-scheduled or manually-scheduled?
Re: Odoo Gantt Chart
Posted: Sun May 29, 2022 2:18 pm
by shatha
We set it auto-scheduled, but in both ways we couldn't move the sub task to Sunday , when i tried it in the demo it works but in our system i couldn't, do you think it a problem from the model it self?
Re: Odoo Gantt Chart
Posted: Tue May 31, 2022 10:22 am
by Terence
Hard to tell. Are there constraints set on the tasks?
Re: Odoo Gantt Chart
Posted: Tue May 31, 2022 12:08 pm
by shatha
Not at all , Could you please provide us with the solution or advice on how to overcome this type of problem?
Re: Odoo Gantt Chart
Posted: Wed Jun 01, 2022 7:57 am
by shatha
How about We can set a meeting with you to show you what we are facing, as well as we can give a remote access through (Team Viewer) to try it . if so please let me know so we can schedule a meeting by tomorrow on Jun 2nd, 2022 11:00 AM GMT timing OR 12:00 PM GMT timing, what would either work for you so i can send you an email about it.