Page 1 of 1

[ANGULAR] The current timeline is not aligned

Posted: Mon Nov 29, 2021 7:35 am
by lanpeng

Hi bryntum
As shown in p2
When the number of Gantt tasks is different, the current timeline is not aligned


Re: [ANGULAR] The current timeline is not aligned

Posted: Mon Nov 29, 2021 10:00 am
by alex.l

Hi lanpeng,

Are you able to reproduce this in our ResourceView example? https://bryntum.com/examples/calendar/resourceview/