When we create dependencies between task, The next task starts the same day as the previous one (see attachment)
Expected behavior : the next tast sarts the end date of previous task +1.
Support Forum
Hello Torence,
I tested with the version 2.0.7, I still have the issue, a 1-day task starts 08/10/2023 and ends 08/11/2023, this is confusing for the users
Is there a way to have the default start hour at 00:00 and the default end hour 23:59
So if I created a task for 08/10/2023 and 1 day duration
Start date will be 80/10/2023 00:00
end date will be 08/10/2023 23:59
We are using 15.0 version for community edition
Thanks
We tried using 8 hours/day, but there is a little issue with this :
- The display in Gantt is not good (only 1/3 of celle is full)
- the duration is not correct : if I create a task that starts 01/01/2023: 08:00 and ends 01/02/2023 16:00 then the duration is 4 days instead of two.
If this is a miss use from our side, can you provide the full configuration to test it?
The display in Gantt is not good (only 1/3 of celle is full)
Yes that's expected I'm afraid since 1 day in that case means 8 hours which is 1/3 of a 24 hours tick.
That look can be changed with the Gantt fillTicks config which will force tasks to fill entire ticks.
the duration is not correct : if I create a task that starts 01/01/2023: 08:00 and ends 01/02/2023 16:00 then the duration is 4 days instead of two.
That sounds like a calendar misconfiguration. I can only guess.. For examples it's 32 hours between the dates and if you by mistake used 24 hours calendar and your project defined hoursPerDay config as 8 then 32/8 = 4
.