Post by troyrob »

Hi, i have a question.

So let's say i have two already existing tasks:

1.2 - Task A
1.3 - Task B

I want to make 1.3 a subtask of 1.2 to look like this:

1.2 - Task A
1.2.1 - Task B

How do i accomplish this?

Or is my only option to delete 1.3 and create a whole new task?


Post by mats »

You can right click and click Indent.


Post by troyrob »

Hi, i don't seem to have that option when i right click

I get:

Edit
Cut
Copy
Equals
Add: Milestone or subtask
Delete


Post by Terence »

Correct, it is not there yet. We have a ticket open for it.

https://github.com/bryntum/odoo-support/issues/85

Will be fixed in the upcoming release.


Post by troyrob »

Terence wrote: Mon Sep 05, 2022 9:12 pm

Correct, it is not there yet. We have a ticket open for it.

https://github.com/bryntum/odoo-support/issues/85

Will be fixed in the upcoming release.

Thank you Terrence, is there any timeline for this release? Indent and Outdent seems like they are fundamental features of a project management GANTT solution.


Post by Terence »

We aim next week to release some fixes.


Post by troyrob »

Terence wrote: Wed Sep 07, 2022 1:12 pm

We aim next week to release some fixes.

Hi Terence,

any update on this?


Post by Terence »

Excuses for the inconvenience, the update was postponed. Aim is upcoming week.


Post by troyrob »

Hi Terrence,

Just following up on this again


Post by Terence »

We got delayed. We are are trying to bundle a couple of updates. Next week it is coming!


Post Reply