Post by sperez »

Team,

The resources field in the standard view mode is not the same than in the Gantt.
When you assign resources and then open the Gantt, are not displayed. Same behavior if you do otherwise.
Looks like there are different fields.

Could you have a look at this, please?

Thank you


Post by Terence »

Hi that is correct we use are own fields to store assignments

We have a ticket to address this:
https://github.com/bryntum/odoo-support/issues/48


Post by sperez »

That is incorrect, the Gantt module should reflect exactly the same what was loaded in Odoo and in the same way if resources are being assigned using your Gantt module.

Please escalate this issue.

Thank you,

Sergio


Post by Terence »

What do you mean by 'was loaded in Odoo' ?

We now use dedicated fields to store assignments, we do not relate to project fields. The underlaying issue is that we first moved from using users to resources as base for assignments. The next step is to reflect this to native Odoo fields.

That ticket will be addressed in the next iteration.


Post by sperez »

Hi there,

Was the code be updated to to reflect this to native Odoo fields?


Post by Terence »

No not yet. We are migrating to Odoo15 first. The issue is on the list after the migration.


Post by valentin c. »

Good day,
I am facing the same issue with our ressources. I am using odoo v15 as well. Do you know when this will be corrected?

Many thanks,
Valentin.


Post by Terence »

We scheduled this for later this year Q2. Possibly part of a new Scheduling module depending on the Employee module.


Post by christos »

Great we are looking forward for this module combining Gantt with schedule pro


Post Reply