Resources can be added on summary tasks which is wrong. Resources on summary tasks must be auto-completed by the sub-tasks in the same way that "Done %" is being done.
This is not only a visual thing. Assignments on parent tasks also effect task scheduling. We would like to keep that option open. We might consider an option to disable assignments on parent tasks.