Post by christos »

Resources can be added on summary tasks which is wrong. Resources on summary tasks must be auto-completed by the sub-tasks in the same way that "Done %" is being done.


Post by Terence »

This is not only a visual thing. Assignments on parent tasks also effect task scheduling. We would like to keep that option open. We might consider an option to disable assignments on parent tasks.


Post by christos »

That option would be great. Or, is there a way to disable subtasks, in other words not to have summary tasks at all ?


Post by Terence »

The chart could be configured that way but is not an Odoo option at the moment.