Post by christos »

Is there a way to add baselines support in odoo gantt ?

I am not familiar with chronograph nor a programmer, I am trying to figure out how odoo-gantt can be configured so we can successfully implement it in our our existing odoo platform.

Thank you!!


Post by Terence »

https://github.com/bryntum/odoo-support/issues/6

I have created a new feature request.


Post by janverstr »

Baselines are available now indeed, but they do not seem to be saved. Even in the demo environment.
Steps

  1. Open the gantt view
  2. Activate baseline
  3. Set a baseline (e.g. 1)
  4. Move a task
  5. Close the view
  6. Reopen the view
  7. Activate baselines
  8. All baselines will be at the current position of the task and not where you saved baseline 1.

Post by Terence »