Good afternoon, there is the following situation.
- The backend returns a response to load with slightly inconsistent data, incorrect dates
- After downloading, gantt fixes them, which is true.
- However, an attempt to save the corrected data (sync()) does not lead to anything.
Can you tell me if it is possible to force the entire store to be resaved? To correct the "wrongness" of the data
That should happen automatically, any chance you can drop us a small test case with data so we can debug it?
Yes, on the UI it happens automatically.
However, these changes are not considered changes (an empty array is returned if gantt.project.changes is requested)
As a consequence gantt.project.sync does nothing
I need fixes that become visible on the UI to be written to the backend