Good afternoon. Tell me, is it possible to change the direction of the start of drawing the inscription about the beginning of the project in the ProjectLine?
I would like the inscription StartProject to be drawn before the line, and EndProject after. Thus, they will not close the useful calendar area.

Didn't find anything similar in the documentation. I assume that only through overriding an independent rendering method. Or am I wrong?


Post by alex.l »

It is not supported now and really tricky to change the position for start project line only. I've opened a feature request here: https://github.com/bryntum/support/issues/4021

All the best,
Alex


Post by tikhonov.a.p »

Alex, thank you. Then I will not make a bike and wait for the feature.


Post by tikhonov.a.p »

Good afternoon, what is the status?


Post by alex.l »

No information for now. I asked our product management to check that again and put a milestone if possible.
You can subscribe on ticket updated to be notified.

All the best,
Alex