Hello,
We are observing a behavior when if you zoom into a day's view for a task on the chart side and then try to drag the end date to a middle of the day. We can see that duration column gets changed to a fractional value.
Which affects the overall schedule by reshuffling the dependent tasks, is this an expected feature or there is a way to control the duration column during a drag to only allow for whole day movements and not fractional ?
How can we reproduce this?
It is possible to create a fractional task duration value by doing the following :
a) Use the zoom in button in the tool bar to zoom in a bit, such that the visual representation of a day can be seen on the gantt chart
b) Then dragging the end date of a task to the middle of a of a particular day, we can see that the duration column gets updated a fractional value.
Hi awendt,
Yes, that you described - is an expected behaviour. duration units used to comfortable user experience, but duration may be in a middle as well.
All the best,
Alex