Our state of the art Gantt chart
Hi Team ,
We are facing this kind of issue , but we have no clue . What would be the possible reason for this issue. I have attached the screen shot of the same below.
-
Attachments
-
- MicrosoftTeams-image (6).png (58.38 KiB) Viewed 334 times
Look at the error message - it tells you there is cyclic relationships in your data (not allowed). Please sanitize your data and all will work fine!
May I know what do you mean by cyclic relationships? Can you please explain briefly
It means your dependencies end up in a circular pattern, meaning the calculation engine won't know what to do with your schedule data.
Look again at the message and you see how the task cycle is formed. Just remove the bad dependencies and it'll work fine again.