Hello there!
We have a problem with the start/end date relationship. The same can be confirmed in the example project. https://www.bryntum.com/examples/gantt/advanced/
The start date is Jan 14, 2019, and the end date is Jan 16, 2019, and the duration is only 2. Why it is not 3 days? Jan. 14, 15, 16?
Acceptance criteria:
Task end date timestamp should always end on the last working day
a day used in task start and end date always starts at 00:00:00 and ends at 23:59:59
Task with duration = 1 starts and ends on the same day ("task takes 1 day")
Task with duration =2 ("task takes 2 days")
start = n
end = n+1
Find an example here:
How can we achieve this?