Hello dears,
I am using the gantt-2.1.9 component and I would like to know how to configure it so that the "finish" or "end date" column has the same behavior as Microsoft Project.
Microsoft Project's behavior:
A task that starts on day 1 with a duration of 1 day, ends on the same day
A task that starts on day 1 and lasts for 5 days, ends on day 5
Bryntum Gantt's behavior:
A task that starts on day 1 with a duration of 1 day, ends on the following day
A task that starts on day 1 and lasts for 5 days, ends on day 6
Attached a comparison of MS Project with the Bryntum Gantt demo at:
https://www.bryntum.com/examples/gantt/react/javascript/advanced/build/index.html
Thanks
Tiago Lima