Hello,
In the Gantt when you create new tasks the Successor and Predecessors show "phantom ids" which are not easy to read by users, is it possible to change it to WBS values (like 1, 1.1, etc) or others?, if so how?
An example of this attached.
Hello,
In the Gantt when you create new tasks the Successor and Predecessors show "phantom ids" which are not easy to read by users, is it possible to change it to WBS values (like 1, 1.1, etc) or others?, if so how?
An example of this attached.
Hello,
It's not supported at the moment, but we're working on it. Stay tuned!
https://github.com/bryntum/support/issues/681
Best,
Pavel
Pavlo Miklashevych
Sr. Frontend Developer
Hello,
I see that this is fixed and working in the bryntum examples (online), we have a similar related case that is showing the internal ids instead of the sequence, running the examples directly in version 4.0.5 seems to be using the id of the task and not the sequence, how can we change to use a custom data or the sequence of the task?
(I cannot find in the documentation of the useSequenceNumber explained in the github)
Thanks,
Hi daniel.piret,
Yes, because that property has a different name in the new Gantt.
Please check here: https://bryntum.com/docs/gantt/#Gantt/widget/DependencyField#config-dependencyIdField
And here: https://bryntum.com/docs/gantt/#Gantt/view/GanttBase#config-dependencyIdField
All the best,