Calendars are giving me some strange results. I have checked on your website and am getting the same issues. Switching between calendars and back again affects the original duration. I have created a video for you to see below;
https://www.loom.com/share/6cf9cea59c6a4e47a9ce60721abac2a5
Other issues i am getting on my calendars are;
I want to have a 1 day duration that starts and finishes on the same day, e.g Start at 8:00 & Finish at 17:00, this seems not possible. The only way to show a task starting & finishing on the same day is to create a milestone - but I need to have a 1 day task. Is there a way to set this up?
Also see image below, can i stop this situation occurring - I clearly have a task running over 3 weeks but the duration is 5 days. There is no effort applied or constraints - this should be 15 days??
I have spent so much time trying to resolve these issues, can someone give me a demo please on how all this should be managed. I would really appreciate it as it is very frustrating.