Our state of the art Gantt chart


Post by Jerther »

Here are the steps to reproduce:

  • Open the Basic demo
  • Add a new root task at the top
  • Edit the task
  • Change the effort to 40 hours
  • In the advanced tab, select Effort Driven, then fixed units
  • Save
  • Add a new task below this one. This creates a copy.
  • Now drag a dependency from the start of the first one to the beginning of the second one.

Result:
The second task is move all the way to the end of the project

Expected:
The second task is moved to the end of the first one.

I understand Fixed Units requires some assignments. But that's still weird ;)


Post by alex.l »

Hi Jerther,

I was able to reproduce this. You are right, it might be better. Here is a ticket https://github.com/bryntum/support/issues/839

Thanks,
Alex

All the best,
Alex


Post by Jerther »

I just tested this again in the Basic demo and it does not happen anymore. So I guess this is obsolete.


Post Reply