Here are the steps to reproduce:
- Open the Basic demo
- Add a new root task at the top
- Edit the task
- Change the effort to 40 hours
- In the advanced tab, select Effort Driven, then fixed units
- Save
- Add a new task below this one. This creates a copy.
- Now drag a dependency from the start of the first one to the beginning of the second one.
Result:
The second task is move all the way to the end of the project
Expected:
The second task is moved to the end of the first one.
I understand Fixed Units requires some assignments. But that's still weird