Our state of the art Gantt chart


Post by Borja »

Hi there,

Here is the initial situation: we have a manual task (line 90) and a dependant automatic task (line 100): see image 1.

When the duration of the manual task is changed from 5 to 10 days, the dependant automatic task is also moving: see image 3. This is correct.

However, if we change the start date of the manual task, then the dependant automatic task is not moving at all, but it should since it is automatic task. See image 4.

Could you please check?

Thanks and Regards,
Borja

Post by pmiklashevich »

Hello Borja,

I see no screenshots attached, but I've reproduced the issue. Thanks for good description!
https://github.com/bryntum/support/issues/733

Best,
Pavel

Pavlo Miklashevych
Sr. Frontend Developer


Post by Borja »

Hi there,

Here the missing images. Regards.

Manual task:
captura 1.PNG
captura 1.PNG (52.07 KiB) Viewed 1674 times
Moving the manual task when changing duration is working ok:
Captura 3.PNG
Captura 3.PNG (45.01 KiB) Viewed 1674 times
Changing the initial date of the manual task, does not move the dependent automatic task:
Captura 4.PNG
Captura 4.PNG (58.84 KiB) Viewed 1674 times

Post by pmiklashevich »

I recreated the case by the description you provided! But thanks anyway :)

Pavlo Miklashevych
Sr. Frontend Developer


Post by nickolay »

The fix has landed to the sources, you can verify it in the tomorrow nightly build.

Post Reply