How to use Feature of As soon as possible for Constraint Type? or can we integrate ?
Support Forum
Unfortunately As Late As Possible constraint is not supported yet. But we certainly have plans on implementing it.
In general initial implementation of critical path method related API will appear in the upcoming release of the Gantt.
Among other new features the release will include new critical paths feature (highlighting the project critical paths) and new related columns (early start/end, late start/end and total slack).
The Gantt is improving day by day and ALAP constraint will be implemented for sure. So stay tuned!