Post by aydinozturk »

Hello again :)

How to use Feature of As soon as possible for Constraint Type? or can we integrate ?

Image

Post by pmiklashevich »

We don't have "as soon as possible" constraint explicitly specified, but all scheduling processes follow this pattern by default. We will introduce such constraint together with backwards scheduling in the future. But meanwhile it's redundant.

Pavlo Miklashevych
Sr. Frontend Developer


Post by aydinozturk »

okay,
If we want to get the " as late as possible" field when we transfer with MS Project. Does Schedule cause problems ? and How to use in gantt column " late finish / late start "

Post by arcady »

Unfortunately As Late As Possible constraint is not supported yet. But we certainly have plans on implementing it.

In general initial implementation of critical path method related API will appear in the upcoming release of the Gantt.
Among other new features the release will include new critical paths feature (highlighting the project critical paths) and new related columns (early start/end, late start/end and total slack).

The Gantt is improving day by day and ALAP constraint will be implemented for sure. So stay tuned! :)