Our state of the art Gantt chart


Post by SIM-LTD »

Hi there

We are facing a couple of issue with the Task rendering...

In order for you to reproduce it, just take the "Basic Demo" and make the same test as we ran

1) When clicking onto a Parent Task (Summary Task) and click right to add a task below.
Then, a Parent Task is added. Why a Parent?

2) When clicking onto a Child Task (basic Task) and click right to add a task below.
Then, a child Task is added. But other tasks disappear

Why adding a task leads to add the same type of selected Task?

After having added a task, then all the dependencies are no longer rendered as it should be.
Attachments
Capture d’écran 2019-05-20 à 10.12.16.png
Capture d’écran 2019-05-20 à 10.12.16.png (103.57 KiB) Viewed 817 times
Capture d’écran 2019-05-20 à 10.12.33.png
Capture d’écran 2019-05-20 à 10.12.33.png (99.87 KiB) Viewed 817 times
Capture d’écran 2019-05-19 à 11.17.04.png
Capture d’écran 2019-05-19 à 11.17.04.png (108.94 KiB) Viewed 817 times

Post by mats »

This is a bug yes, ticket opened here: https://app.assembla.com/spaces/bryntum ... nt/details#

Thanks for reporting!

Post Reply