Hi support team,
I have a scenario as:
I create a template to reuse later. For example my template was created from Aug 01 2020. It means Start Date of template project also Aug 01 2020. Now I use this template for new project with Start Date is Oct 04 2021. The problem I faced that the template I used was created from 2020, so its holidays totally difference with 2021. So my expectation that after project loaded, I want to force the button sync is enable and can sync all tasks again. Why I need to able to sync at the first time when project loaded? Because Bryntum Gantt will auto update Start & Finish based on calendar of the year 2021 that I passed.
Here is my code after applied the template:
And here is image of data above loaded on Bryntum Gantt. Start & Finish Date are totally difference with the code above. but I don't know why the button save is disabled
Please help me how to force enable to save all tasks?
Thanks