Hello,
Certain customers have their weekends on Fri and Sat and working days goes from Sunday to Thursday, we have tried to change the calendar from this:
"intervals": [{
"recurrentStartDate": "on Sat at 0:00",
"recurrentEndDate": "on Mon at 0:00",
"isWorking": false
},
to this:
"intervals": [{
"recurrentStartDate": "on Fri at 0:00",
"recurrentEndDate": "on Sun at 0:00",
"isWorking": false
},
But now the Gantt Calendar shows Friday, Saturday and Sunday as grey (non-working days), if I add a task starting on Thursday with duration 2 days it starts on Thursday and finish on Monday, as the non-working day is selected as Fri/Sat I would expect that it should be completed on Sunday, so how do I change the default weekends?
I cannot find in the documentation how to change the default Weekends, can you point me in the right direction please?
Thanks