I have AnotherStartDate and AnotherFinishDate in my task data set. I want to draw that as a "shadow activity" in the gantt. Would that be possible? (see image)
I did try using indicators but it does not look like it will support endDate
You manage to do it with the early and late dates. So I want the exact same posibility with a custom time span
You are referring to baseline, as I already wrote, we have already implemented baselines, and that is working fine!
What I want is something else, something that is similar to "lateDates" and "earlyDates" as you have in your documentation for indicators. But do you have any examples for how I can make something similar like the lateDates, as an indicator