Premium support for our pure JavaScript UI components
Hello guys!
We have a problem of data binding.
We use "this.project.instance.inlineData;"
After task is opening - the combo is empty and not valorized (no any error in console).
The same code works in Scheduler Pro, but not in Gantt and we canot figure out why?
Attached project if you need it.
Your help will be greatly appreciated!
- a1.png (714.49 KiB) Viewed 411 times
- a2.png (731.92 KiB) Viewed 411 times
Hi,
I've checked the data that is coming from the API endpoint, it doesn't have any property called project_id
or development_id
. I think this is why it's not showing the values in the combo.
Hello Tasnim, do you mean the datasource?
Inside of datasource we have these fields.
- w1.png (477.63 KiB) Viewed 395 times
I'm talking about this
- Screenshot 2022-07-04 101009.png (119.82 KiB) Viewed 359 times