Hey Guys,
We want to display task information in other places in our app (e.g. a task linked to another resource shown on another dashboard). Our projects have on average 2.5k tasks. We want to display the WBS number along with the task name in these circumstances. I've set the wbs to alwaysWrite, and that's been working ok. However we've found that changes to the wbs structure (e.g. adding a task) will only affect sibling tasks, I assume as a side effect of the parentIndex property changing, and no changes to the children of those siblings.
The effect in our DB is that we have a task that's been updated to e.g. 1.4, and all it's children remain as 1.3.*.
How can we remedy this?
Thanks
Chris