Hi Guys

Where could I find some documentation about how the gantt dates work.

We are using it with manuallyScheduled set to false and we are seeing lots of weirdness with the dates.

Where could we find documentation about how constaints, earlyStartDate, startDate, projectStartDate all link together and which has higher priority please.

Thank you


Post by mats »

This guide describes how the task scheduling works: https://bryntum.com/docs/gantt/#../engine/gantt_events_scheduling.md


Post by david10sing »

Thank you Mats