Hey Guys,
In the advanced demo https://www.bryntum.com/examples/gantt/advanced/, edit a task, set the duration to 1290 days, then try increase by another day, the end date rolls around to an earlier date.
Cheers,
Chris
Hey Guys,
In the advanced demo https://www.bryntum.com/examples/gantt/advanced/, edit a task, set the duration to 1290 days, then try increase by another day, the end date rolls around to an earlier date.
Cheers,
Chris
There is a private config limiting calendar iterations longer than 5 years roughly. It's purpose is to stop infinite iteration in case of a calendar misconfiguration.
Here is a ticket to make it public: https://github.com/bryntum/support/issues/2962
And so far to override this value you can use the code like this:
// subclass standard CalendarModel class
class MyCalendarModel extends CalendarModel {
// override its calendarCache property
get calendarCache() {
const result = super.calendarCache;
// to change its maxRange to some custom 10 years value
result.maxRange = 10 * 365 * 24 * 60 * 60 * 1000;
return result;
}
}
new Gantt({
project : {
// tell project model that we want to use custom calendar model class
calendarModelClass : MyCalendarModel,
...
Related forum post where this topic was also discussed recently: viewtopic.php?f=52&t=17668