Hi,

I have set autoSync=true in the advanced example of gantt v5.0.0 and loaded this schedule:

testing.json
(47.43 KiB) Downloaded 49 times

When I load a schedule containing illegal links (same parent as predecessor), and get the dialog to remove/deactivate dependency, applying does not trigger sync:

I.JPG
I.JPG (305.79 KiB) Viewed 507 times

Is this a bug, or intentional?

Thank you


Post by alex.l »

That looks like a bug, here is a ticket: https://github.com/bryntum/support/issues/4341

Thank you for the report!

All the best,
Alex


Post by fdyrs »

Hi,

When do you think this will be solved? :-)


Post by tasnim »

Sorry, we can't say anything about that. As its milestone is set to 5.0.X, it might be solved in our next minor release.