Post by Emilio Premium »

Hello.
When I select Continue. Remove the Finish no later than constraint , it removes the constraint but put back the task on its previous date. But I want it to continue the changes which I initiated If I remove the constraint applied on it.
Steps to reproduce-
Create 1 Task
set FNLT constraint on it
move the task in right
it will popup the window
choose option 2nd
According to user , it should allow the task to go on the date I dropped it on if I removed the constraint , but It does not. It may be occurred in other constraint type too.
Thanks


Post by arcady »

Reproduced. It's a bug and here is a ticket for it: https://app.assembla.com/spaces/bryntum/tickets/9676-unexpected-constraint-field-reset/details
Thank you for the report!