Support for v6.x of our Scheduling components


Post by inspire »

Hi!

I am wondering if there is some limit for Lag value (both min and max) in Dependency fields.
When I set Predecessor value as <Row_Number>+1300 Gantt does not recalculate dependent row start/finish dates. Looks like recalc logic does not trigger at all on these numbers. Then I change Predecessor value to <Row_Number>+1250 and it works.
Is there some limit for Lag value, I did not find it in documentation.
Thanks.


Post by Maxim Gorkovsky »

Hello.
You seem to be limited by the maximum calendar range. We do not have a public config yet, but there is a ticket to document it: https://github.com/bryntum/support/issues/2962
Please check this forum post for a workaround: viewtopic.php?f=51&t=18256&p=90303&hilit=maxRange#p90303


Post by inspire »

Maxim Gorkovsky wrote:
Wed Nov 03, 2021 12:56 pm

Hello.
You seem to be limited by the maximum calendar range. We do not have a public config yet, but there is a ticket to document it: https://github.com/bryntum/support/issues/2962
Please check this forum post for a workaround: viewtopic.php?f=51&t=18256&p=90303&hilit=maxRange#p90303

Sorry but as I can see this will work in new non ext js version. Is it true?


Post by Maxim Gorkovsky »

For ExtJS there is a public config to change maximum calendar range: https://bryntum.com/docs/gantt-for-extjs/#!/api/Gnt.data.TaskStore-cfg-availabilitySearchLimit By default it is 5 years. Please try increasing it to see if it helps with your long lag?