@tasnim,
Anyway we can get this feature in Bryntum gantt? We are trying to highlight the non working days in Bryntum gantt, but seems like after giving the configs, it is still not working...
Non-working time for SchedulerPro and Gantt are driving by calendars.
Project and/or task and/or resource may have own calendar with working and non-working time periods.
When you set calendar for a resource and apply it to some task, that task will be scheduled according to that calendar.
Gantt doesn't support resource non-working time visualization now, only project's calendar may be displayed on timeAxis. But all tasks will be scheduled correctly according to your specifications.
Thanks Alex,
I was able to add/remove nonworkingtime from the gantt, but when I dod it dynamically, only when I do a zoomin or zoomout (essentially when I do change the view layout), the newly added nonworking times are getting reflected on the UI. I think I am missing something to refresh the view.
Is there anyway I can achieve that?