Hi,
Running into the online demo (https://www.bryntum.com/examples/scheduler/partners/) to implement the Partner Timelines, we realized that sometime Schedulers are not Sync
To reproduce it, simply use the ZoomIn or ZoomOut button and you'll see at a certain point the Sync are lost.
But, once scrolling from one Scheduler, then the Sync gets back.
Support Forum
Confirmed, ticket opened: https://app.assembla.com/spaces/bryntum/tickets/8764-partner-timelines-out-of-sync-after-zooming/details#
Thanks for reporting!
Thanks for reporting!
Hi,
We are entering the phase of our project where now we need to implement the "Partner".
And for that, we need to know when those issues will be fixed :
we did not make much progress:?
As a matter of fact :
1) We cannot figure out how to set the Scheduler beneath the Gantt.
As you see, the Gantt seat next to the Scheduler, even if in the css we have :
So if you could give us a small hint on how to ensure both Gantt & Scheduler remains under each other; that would be nice.
Nonetheless, the main point remains entirely open: When those issues will be fixed since we cannot move forward in implementing our process "Partner" since there are too many issues already posted and under tickets.
To be honest this is getting a bit urgent for us since we are getting a bit behind our project schedule.
Please have a glance on the Gif herewith, you'll notice that all issues highlighted, above, are visible in the small Gif animation :
... Timeline is broken when scheduler partners gantt
... When scheduler partners gantt zoom in out fails with exception
... etc...
Thank you for your return
We are entering the phase of our project where now we need to implement the "Partner".
And for that, we need to know when those issues will be fixed :
- 1) #8764: Partner timelines out of sync after zooming
2) #8541: When scheduler partners gantt locked grid width is taken randomly either from
3) #8542: Timeline is broken when scheduler partners gantt
4) #8543: When scheduler partners gantt zoom in out fails with exception
5) #8564: Gantt normal grid gets shrunk when using the splitter
we did not make much progress:?
As a matter of fact :
1) We cannot figure out how to set the Scheduler beneath the Gantt.
..... Gantt({
flex : '1 1 50%',
minHeight : '20em',
})
..... Scheduler({
partner : gantt,
flex : '1 1 50%',
minHeight : '20em',
})
<style lang="scss">
.app_gantt {
display : flex;
height : 100%;
flex-direction : column;
};
Nonetheless, the main point remains entirely open: When those issues will be fixed since we cannot move forward in implementing our process "Partner" since there are too many issues already posted and under tickets.
To be honest this is getting a bit urgent for us since we are getting a bit behind our project schedule.
Please have a glance on the Gif herewith, you'll notice that all issues highlighted, above, are visible in the small Gif animation :
... Timeline is broken when scheduler partners gantt
... When scheduler partners gantt zoom in out fails with exception
... etc...
Thank you for your return
- Attachments
-
- Enregistrement de l’écran 2019-07-30 à 14.35.43.gif (724.47 KiB) Viewed 1430 times
Hello,
We're releasing new Gantt version this week. Also we're going to introduce Scheduler Pro version which will be more compatible with Gantt. So partnering them should be much straightforward. Nevertheless we will check all the known issues against new release and will fix all the found issues in the follow up patch-release. So it's about 2-3 weeks to make partnering is completely supported. Please stay tuned!
Best,
Pavel
We're releasing new Gantt version this week. Also we're going to introduce Scheduler Pro version which will be more compatible with Gantt. So partnering them should be much straightforward. Nevertheless we will check all the known issues against new release and will fix all the found issues in the follow up patch-release. So it's about 2-3 weeks to make partnering is completely supported. Please stay tuned!
Best,
Pavel
Pavlo Miklashevych
Sr. Frontend Developer
Hi
Thank you for your return.
You mentioned "Scheduler Pro" Will this fully compatible with "Scheduler" 2.2.1 'release July 24th'.
Our worries are since we have bought a license End of March and just took over that component, so as to implement an important project;
we cannot afford now, in the middle of the project, to migrate all our processes to a new version called "Scheduler PRO"
Thus we really hope the new "Scheduler Pro" is fully compatible (minor adjustment can be handled); Otherwise, that could be an issue for us
Is there a place (web page) where we can see the value-added : Scheduler Pro versus Scheduler Standard JavaScript 2.2.1 ?
Meanwhile, we'll be waiting for the new Gantt release this week.
Thank you for your return.
You mentioned "Scheduler Pro" Will this fully compatible with "Scheduler" 2.2.1 'release July 24th'.
Our worries are since we have bought a license End of March and just took over that component, so as to implement an important project;
we cannot afford now, in the middle of the project, to migrate all our processes to a new version called "Scheduler PRO"
Thus we really hope the new "Scheduler Pro" is fully compatible (minor adjustment can be handled); Otherwise, that could be an issue for us
Is there a place (web page) where we can see the value-added : Scheduler Pro versus Scheduler Standard JavaScript 2.2.1 ?
Meanwhile, we'll be waiting for the new Gantt release this week.
Hello,
We understand your concerns. From what I can reveal now Scheduler Pro will use the same CRUD manager Gantt does, which will bring asynchronous data handling. Scheduler Pro will use customized TaskEditor instead of EventEditor. Could you please create a list of widgets/features you've already customized to understand what else to check on compatibility? What is the most critical for you?
Best,
Pavel
We understand your concerns. From what I can reveal now Scheduler Pro will use the same CRUD manager Gantt does, which will bring asynchronous data handling. Scheduler Pro will use customized TaskEditor instead of EventEditor. Could you please create a list of widgets/features you've already customized to understand what else to check on compatibility? What is the most critical for you?
Best,
Pavel
Pavlo Miklashevych
Sr. Frontend Developer
Hi Pavel
Our project is pretty much sensitive and We're not allowed to expose on any public place some piece before the official launching.
Nonetheless, can we send you what we have either customized and used, privately, in order for you to tell if the future release "Scheduler Pro" will require us to reconsider some process we have implemented? (Do not worry we won't send you our project but just a brief description about was is used (Method / Properties / Features / Config / ....)
As you have been with us since the very beginning when we have reported a lot of issues, you may know that we have implemented in one core solution both of your component "Scheduler" & "Gantt" with a high level of CRUD within a Realtime push data.
We also have completely customized the Scheduler "EventEditor".
So we really hope that the new "Scheduler Pro" won't be too far from the current release.
We are a bit stuck now because we cannot fully implement the Partner "features" between Gantt & Scheduler, and must wait 2-3 weeks, according to what you said; Thus please make sure that at least all know the issue will be fixed.
Thank you again for your support and patient
Our project is pretty much sensitive and We're not allowed to expose on any public place some piece before the official launching.
Nonetheless, can we send you what we have either customized and used, privately, in order for you to tell if the future release "Scheduler Pro" will require us to reconsider some process we have implemented? (Do not worry we won't send you our project but just a brief description about was is used (Method / Properties / Features / Config / ....)
As you have been with us since the very beginning when we have reported a lot of issues, you may know that we have implemented in one core solution both of your component "Scheduler" & "Gantt" with a high level of CRUD within a Realtime push data.
We also have completely customized the Scheduler "EventEditor".
So we really hope that the new "Scheduler Pro" won't be too far from the current release.
We are a bit stuck now because we cannot fully implement the Partner "features" between Gantt & Scheduler, and must wait 2-3 weeks, according to what you said; Thus please make sure that at least all know the issue will be fixed.
Thank you again for your support and patient