Please can you tell me how I can add tasks.
In this case :
1.- I selected a task
2.- I show my form
3 .- I add 3 objects with the following formats:
{
"Id" : 1,
"StartDate" : "2017-01-17",
"EndDate" : "2017-01-19"
"Duration" : 2
},
{
"Id" : 2,
"StartDate" : "2017-01-20",
"EndDate" : "2017-01-22"
"Duration" : 2
}
Is there an event or method?
Different from this method :
splitTask: function() {
var a = this,
e = a.grid.getSchedulingView(),
d = e.getDateFromX(a.triggerEventXY[0]),
c = e.timeAxis;
var b = {
task: a.rec,
pos: a.triggerEventXY,
date: d,
timeAxis: c,
tick: c.getAt(Math.floor(c.getTickFromDate(d)))
};
b.task.split(a.getSplitDate(b), a.getSplitDuration(b), a.getSplitDurationUnit(b))
}
Can you tell me how to configure the method to add many segments?
attached image.