Hi,

I am interested for the "Scheduler" product.
Is it possible to replace "End Date" with "Duration" in days?

I looked for the examples in the documentation, but couldn't find this option.
The goal would be to enter the duration of the task and create the task automatically taking into account the off days (Saturday / Sunday).
It's possible ?

Thanks in advance =)


Post by mats »

You can do this in Schedule Pro easily, see demo here: https://www.bryntum.com/examples/scheduler-pro/dependencies/


Post by elucian »

@mats, can this be done with Gantt as well? Forgive the niave question, I am still working thru the docs.


Post by pmiklashevich »

Pavlo Miklashevych
Sr. Frontend Developer


Post by Pytha »

mats wrote: Sun Nov 01, 2020 8:31 pm

You can do this in Schedule Pro easily, see demo here: https://www.bryntum.com/examples/scheduler-pro/dependencies/

Thank you !

We dont have this feature on the basic "Scheduler" ? only on the pro version ?


Post by arcady »

Yes you need Pro version of the Scheduler to have proper support of calendars (non-working Sat and Sun etc.) out of the box.


Post by Pytha »

arcady wrote: Thu Nov 05, 2020 7:53 am

Yes you need Pro version of the Scheduler to have proper support of calendars (non-working Sat and Sun etc.) out of the box.

Perfect, thank you for your help ! :)