Hello,
Please provide the expression you want to construct?
Best regards,
Arcady
Hello,
Please provide the expression you want to construct?
Best regards,
Arcady
P.S. And if text
parser doesn't work for you please keep in mind you can use recur
parser:
later.parse.recur().on(13).hour().every(1).dayOfYear().startingOn(59)
You can put its result to recurrentStartDate
/recurrentEndDate
fields Should work as well.
Duration by definition is amount of working time between start and end dates.
If you expect something else then it's probably not duration but some other custom value. Feel free to add a custom field and calculate it the way you need.
Task 2's duration should be 1 day from users perspective.
Task 2 uses 24/7 calendar so duration between its start and end dates is 24 hours.
Your project specifies that day unit value is 8 hours:
hoursPerDay: 8
So 24 hours duration === 3 days
Hello,
No the Gantt doesn't have elapsed duration support I'm afraid.
Similar effect can be achieved with using a 24/7 calendar for a task (and setting its ignoreResourceCalendar to true if it has assignments).
Best regards,
Arcady
Regarding why your parent task doesn't move - it's hard to tell since you haven't provided a test case.
My guess is it probably contains a manually scheduled child task. Then the parent cannot move since its child position is supposed to be set by user manually.