Search found 1831 matches

by arcady
Fri Mar 15, 2019 8:49 am
Forum: Help and General Questions
Topic: Constraint Type and Date is not getting set on End Date modification
Replies: 12
Views: 727

Re: Constraint Type and Date is not getting set on End Date modification

If I set it to true then then SNET constraint is set as soon as I edit end date.
by arcady
Mon Mar 11, 2019 11:38 am
Forum: Help and General Questions
Topic: Constraint Type and Date is not getting set on End Date modification
Replies: 12
Views: 727

Re: Constraint Type and Date is not getting set on End Date modification

Why would it set a new constraint?
When you change a date in the gantt end date column you resize a task. Given that it's a forward scheduled project I can't imagine a scenario when it should result setting a constraint.
by arcady
Fri Mar 08, 2019 9:18 am
Forum: Help and General Questions
Topic: Constraint Type and Date is not getting set on End Date modification
Replies: 12
Views: 727

Re: Constraint Type and Date is not getting set on End Date modification

rdonahue6 wrote:
Thu Mar 07, 2019 12:36 pm
I am able to reproduce this in Advance example of Bryntum 6.
I cannot reproduce this on our advanced demo. When I move such task I don't see a constrain violation window the task just silently gets SNET constraint pointing its new start position.
by arcady
Wed Mar 06, 2019 8:37 pm
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Late dates and backward pass scheduling
Replies: 5
Views: 314

Re: Late dates and backward pass scheduling

Yes for completed tasks they are equal.
by arcady
Wed Mar 06, 2019 8:18 am
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Late dates and backward pass scheduling
Replies: 5
Views: 314

Re: Late dates and backward pass scheduling

Yes - for both questions. :)
Backward scheduling considers the project finish date and Late dates calculation takes constraints into account.
by arcady
Tue Mar 05, 2019 9:00 am
Forum: Help and General Questions
Topic: Constraint Type and Date is not getting set on End Date modification
Replies: 12
Views: 727

Re: Constraint Type and Date is not getting set on End Date modification

It doesn't work that way out of the box because schedule by constraints mode has appeared quite recently and we haven't got any feedback on this use case yet. I've made a feature request ticket for this: https://app.assembla.com/spaces/bryntum/tickets/7743 But realistically if you need it done quick...
by arcady
Mon Mar 04, 2019 10:36 am
Forum: Help and General Questions
Topic: Constraint Type and Date is not getting set on End Date modification
Replies: 12
Views: 727

Re: Constraint Type and Date is not getting set on End Date modification

Behaviour that you want is not provided out of the box. But it's implementable for sure. Here is the brief changes that should be made: First of all, end date column in MS Project doesn't change tasks duration ..it moves them instead. This is the simplest thing to change. There is a Gnt.column.EndDa...
by arcady
Tue Feb 05, 2019 10:08 am
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Events resize after moving to other resource
Replies: 10
Views: 543

Re: Events resize after moving to other resource

The ticket is resolved now and the fixed version will be available in the next nightly build.
by arcady
Wed Jan 30, 2019 12:22 pm
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Behaviour of task.propagateChanges() compared to taskStore.cascadeChangesForTask(task)
Replies: 4
Views: 245

Re: Behaviour of task.propagateChanges() compared to taskStore.cascadeChangesForTask(task)

Gnt.model.Task does its best to not reschedule tasks when predecessors are not changed. :) We don't have a public way to achieve what you want, but there is a private method called Gnt.model.Task#areLinkedTasksAffectedOrPropagationSourcesLinked . It decides if the task predecessors are changed or n...