Search found 1831 matches

by arcady
Fri Aug 02, 2019 10:35 am
Forum: Help and General Questions
Topic: Export/Print Issue in GanttChart
Replies: 12
Views: 1252

Re: Export/Print Issue in GanttChart

we also tried to use PDF export example which is also not working there. You mean online example? ..yes export server was stopped I've just started it so it's back to live. I see that HTML_for_Export.html file code looks broken: <link href=\"https://<base_Path>/gantt-pro-6.0.8/theme-triton/resource...
by arcady
Fri Jul 19, 2019 4:26 pm
Forum: Bryntum Scheduler
Topic: Release 2.2.0 online demo Vertical Big Data - Does not work
Replies: 1
Views: 60

Re: Release 2.2.0 online demo Vertical Big Data - Does not work

Thanks very much for the report! We'll fix it ASAP.
by arcady
Wed Jul 10, 2019 11:26 am
Forum: Bryntum Gantt
Topic: Brynthum saving custom response data.
Replies: 4
Views: 158

Re: Brynthum saving custom response data.

All custom fields you add to the models are persisted automatically. No need to do any extra setup. :)

You can find an example of defining custom fields in the TaskModel docs ("Subclassing the TaskModel class" chapter): https://www.bryntum.com/docs/gantt/#Gantt/model/TaskModel
by arcady
Wed Jul 10, 2019 7:05 am
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Constraint Types for Tasks
Replies: 1
Views: 118

Re: Constraint Types for Tasks

Yes, looks like we forgot to mention those constraints. It should be finishnoearlierthan (can be checked in the corresponding constraint class docs, Gnt.constraint.FinishNoEarlierThan in this case has gntconstraint: finishnoearlierthan alias, string after ':' is used for those strings). Here is a ti...
by arcady
Tue Jul 09, 2019 2:39 pm
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Advanced Gannt Split Task Problem
Replies: 10
Views: 400

Re: Advanced Gannt Split Task Problem

The ticket is resolved so fixed version is available in the next nightly build and of course will be included in the next 6.0.12 release.
by arcady
Tue Jul 02, 2019 11:47 am
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Constraints on manual tasks
Replies: 9
Views: 315

Re: Constraints on manual tasks

I'm sorry but we don't consider this as a bug. We've also checked what MS Project does in this case and it doesn't reset the constraint as well. If you need this behaviour badly and want us to implement it please contact sales at bryntum.com (more details on professional services are here: https://w...
by arcady
Mon Jul 01, 2019 1:36 pm
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Constraints on manual tasks
Replies: 9
Views: 315

Re: Constraints on manual tasks

Well that's an easy thing to change, just override Gnt.model.Task class setManuallyScheduledWithoutPropagation method something like this: Ext.define('MyApp.model.Task', { extend : 'Gnt.model.Task', setManuallyScheduledWithoutPropagation : function(value) { var me = this; var result = me.callParent(...
by arcady
Mon Jul 01, 2019 12:36 pm
Forum: Ext Scheduler + Ext Gantt 6.x
Topic: Constraints on manual tasks
Replies: 9
Views: 315

Re: Constraints on manual tasks

I don't think it's a bug. A constraint could be set explicitly by user and in this case the gantt cannot just silently remove it.
by arcady
Wed Jun 19, 2019 2:55 pm
Forum: Bryntum Gantt
Topic: How to use Feature of As soon as possible for Constraint Type ?
Replies: 3
Views: 151

Re: How to use Feature of As soon as possible for Constraint Type ?

Unfortunately As Late As Possible constraint is not supported yet. But we certainly have plans on implementing it. In general initial implementation of critical path method related API will appear in the upcoming release of the Gantt. Among other new features the release will include new critical pa...
by arcady
Fri Jun 14, 2019 9:21 am
Forum: Bryntum Gantt
Topic: Project not saving and updating in database
Replies: 20
Views: 656

Re: Project not saving and updating in database

It's hard to say without seeing the code. We need a proper runnable test case to assist you.