I removed some of the tasks for clarity!

See below video from logging in to your website, the bug persists.

https://www.loom.com/share/4b306590ba5c4bd18c94dfd1e8e5fc55

You have not answered the query on a 1 day task, start and finish should be on the same day

Check the latest video, this is how you can recreate the calendar bug in the latest Gantt.

https://www.loom.com/share/2b9017001f0a4633abf5e63663d226f5

On your website Gantt example, extend the end date of one of your tasks thereby increasing the duration. Then do exactly as I did in the video and you will get the same bug.

Is a 1 day task possible without the dates spanning 2 days? A 1 day task should start & finish on the same day.

Calendars are giving me some strange results. I have checked on your website and am getting the same issues. Switching between calendars and back again affects the original duration. I have created a video for you to see below; https://www.loom.com/share/6cf9cea59c6a4e47a9ce60721abac2a5 Other issues...
Hi We are using the Gantt to create Projects and also Programme views containing multiple Projects, so with the hierarchy below we can view a project separately [Project 1] or we can view all projects together [Programme 1]; Programme 1 Project 1 Project 2 Project 3 etc... When we look at projects i...
Thank you
I experienced this issue on your demo website, as well as our version. When will the fix be incorporated into the product?
If I check the Hide Schedule in Features, then reorganise the columns then uncheck Hide Schedule again all my tasks dissappear, leaving only the relationship lines! In the example on your demo site I also slid the schedule panel to the right using the > arrow, then shifted the Status column adjacent...