This issue can be reproduced easily in example project "Loading data from MS Project"(https://dev.bryntum.com/examples/gantt/examples/msproject_import/) When assigning a resource to a task in task editor form, resources in combo list are not sorted. https://forum.bryntum.com/download/file....
Thanks Saki.
It is Gantt For Ext JS and the version is Gantt Pro 6.0.12.
It is Gantt For Ext JS and the version is Gantt Pro 6.0.12.
In Ms project, the defaultAvailability of "24 Hours" calendar is [00:00-00:00], after a .mpp file is imported into Bryntum gantt. Duration [00:00-00:00] is considered to be zero. https://forum.bryntum.com/download/file.php?mode=view&id=8684 Seems it can work after I update [00:00-00:00...