This issue can be reproduced easily in example project "Loading data from MS Project"(https://dev.bryntum.com/examples/gantt/examples/msproject_import/) When assigning a resource to a task in task editor form, resources in combo list are not sorted. https://forum.bryntum.com/download/file....
Thanks Saki.
It is Gantt For Ext JS and the version is Gantt Pro 6.0.12.
In Ms project, the defaultAvailability of "24 Hours" calendar is [00:00-00:00], after a .mpp file is imported into Bryntum gantt. Duration [00:00-00:00] is considered to be zero. https://forum.bryntum.com/download/file.php?mode=view&id=8684 Seems it can work after I update [00:00-00:00...