Search found 4 matches

Thank you very much, really helped me!

Best regards,
Bence Nagy
Thank you very much your quick reply! Currently we are using Ext js 4.x. (We are implementing the changes which are required for upgrading Ext js 6.x). So for the time being we are using Gantt 2.5.4, could that be there is no adjustToCalendar function? Or there is some other function in version 2.5....
Hello! There is two items called A and B. Item A dates: 2015-09-21 => 2015-09-23. Item B dates: 2015-09-24 => 2015-09-28. (So there is no day between this two tasks) Between A and B there is a link (Finish to start) and the lag is two days. When I load the chart item B start date is 2015-09-24 despi...
Hello! I have a question with Gantt dependencies. When I load the Gantt chart despite that between two tasks there is a lag (2 days) this is not taken into account. After moving predecessor element the successor element is cascaded and the link lag is taken into account. I attached a very simple use...