Search found 19 matches

I think it would be Scheduler for Ext JS.
Could you please guide me to the link to the product forum. I am not able to find it.
Can we show the summary task on the scheduler view in the same way just like we show on gantt? Please refer the bars for summary task 1 and summary task 2 in the below image.
summary-task.png
summary-task.png (21.66 KiB) Viewed 917 times
We are in the process of creating a spec for the scheduler view that we can share with you so that you can custom build the scheduler view for us. How do you display the exception (working/non-working) on the scheduler view for a specific day? We may have multiple exceptions on the same day for the ...
In our tool, a task can be assigned to different resources. Each of these assigned resources may belong to the different timezone and hence the start and finish of a task are different for each resource. So for a task can we show different start and finish for different resources on the scheduler vi...
Can we show the unassigned section on the scheduler view? Something similar to the below view:
unassigned section.png
unassigned section.png (36.67 KiB) Viewed 2307 times
Is it possible to show a full taskbar for a day when the working hours for a user is less than 24 hours? 24 hours is treated a one full day in all the scheduler view examples in Bryntum, but in general, 8 working hours make a full working day for a user. So if we assign a task to the user for a day,...
When a new task is created from the scheduler view, the scheduling mode of the task is automatic. What is the default scheduler type? Is it a Fixed Units, or Fixed Duration, or Fixed Work?
No, I am talking about one assignment unit only. Let me explain this with an example. 1. Task 1 duration is 2 days, starts on 1-Jan 8 am and finishes on 2-Jan 5 pm. 2. R1 is assigned 100% (R1 works 8 hours a day 8 am - 12 pm and 1 pm to 5 pm) 3. So the total effort is 16 hours. (1-Jan 8 hours and 2-...
We would like to understand, how to show the per day allocation on a taskbar in the scheduler view. Refer this screenshot rolled up hours.png Here you will see that the per day allocation in mentioned on the taskbar. E.g. For Task 4, it is 8 hrs/day (64hrs). Now it is not possible for us to show it ...