Backward Scheduling demo

This demo shows Backward Scheduling mode of the Gantt. In this mode the Gantt by default schedules all the tasks from the project end date. The mode can be changed in the "Project information" dialog (right click on the "PROJECT A" record and pick the "Project information..." menu entry.

Also pay attention to the "ASSIGN RESOURCES" task which is scheduled ASAP due to its "As soon as possible" constraint (while the rest of the tasks are scheduled ALAP).